Construction Update – September 10, 2024
Construction Update – September 6, 2024
Construction Update – September 3, 2024
Construction Update – August 30, 2024
Construction Update – August 28, 2024
Construction Update – August 23, 2024
Construction Update – August 16, 2024
Construction Update – August 9, 2024
Construction Update – August 2, 2024
Construction Update – July 29, 2024
Construction Update – July 19, 2024
Construction Update – July 12, 2024
Construction Update – July 8, 2024
Construction Update – June 28, 2024
Construction Update – June 21, 2024
Ivy Construction Update – June 14, 2024
Ivy Construction Update – May 31, 2024
Ivy Construction Notice – May 17, 2024
Project Update – May 14, 2024
Dust Monitoring Summary
Cleanup Announcement
July through August 2023
In July and August, our vendors remediated contaminated soils. Soils that exceed health risk standards were safely removed and taken to an appropriate landfill. Soils with lower contamination levels were managed in accordance to a plan approved by both the Minnesota Pollution Control Agency and Minnesota Department of Agriculture. This process was monitored closely by an environmental engineer.
August through December 2023
We anticipate soil remediation will be complete by the end of October. Mass grading on remediated soils will continue until the ground freezes. Water will be applied to soils throughout remediation and grading to minimize dust particles in the air.
2024
We expect to start roadwork construction in the Spring of 2024 and complete mass grading during the first half of 2024. Click to learn more about soil conditions and discussions around air quality and water quality throughout construction.
Site Map
Project Timeline
This timeline is subject to change.